CITY of RAPID CITY

Agenda Item Summary

 

Public Works Committee Meeting Date: 4/28/2015

City Council Meeting Date: 5/4/2015

Staff Contact: Sara Odden

Petitioner: City of Rapid City

Location: 9th Street, Fulton Street and South Street

Agenda Title:

Authorize Staff to Advertise for Bids for 9th Street Reconstruction, Project No. 14-2208 / CIP No. 50435. Estimated Cost: $2,050,000.

 

Summary:

Re-construction of water mains, sanitary sewer mains, service lines and storm sewer in 9th Street from Fulton Street to Columbus Street, Fulton Street from Mt. Rushmore Road to approximately 150’ west of 9th Street and South Street from Mt. Rushmore Road to 9th Street.  Storm sewer installation in 9th Street from Columbus Street to Kansas City Street.  Reconstruction of street and curb and gutter is also included.

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

CIP

Streets

 

CIP

Water

CIP

Wastewater Improvement

 

 

 

CIP

Drainage

 

 

 

 

X

Budgeted

 

 

Not Budgeted

Recommendation:

Action: Approve

Notes:

City Council Options:

 

Attachments & Links:

Advertising Authority

Project Location Map

 

 

 

 

Click here to enter text.

Click here to enter text.

Click here to enter text.